Analysing the effectiveness of different offshore maintenance base options for floating wind farms
Avanessova, Nadezda and Gray, Anthony and Lazakis, Iraklis and Thomson, R Camilla and Rinaldi, Giovanni (2022) Analysing the effectiveness of different offshore maintenance base options for floating wind farms. Wind Energy Science, 7 (2). pp. 887-901. ISSN 2366-7451 (https://doi.org/10.5194/wes-7-887-2022)
Preview |
Text.
Filename: Avanessova_etal_WES_2022_Analysing_the_effectiveness_of_different_offshore_maintenance_base_options_for_floating_wind_farms.pdf
Final Published Version License: Download (1MB)| Preview |
Abstract
With the growth of the floating wind industry, new operation and maintenance (O&M) research has emerged evaluating tow-to-port strategies , but limited work has been done on analysing other logistical strategies for offshore floating wind farms. In particular, what logistical solutions are the best for farms located far offshore that cannot be reached by crew transfer vessels (CTVs)? Previous studies have looked at the use of surface effect ships (SES) and CTVs during the operation and maintenance (O&M) of bottom-fixed wind farms, but only some of them included service operation vessels (SOVs). This study analyses two strategies that could be used for floating wind farms located far from shore using ORE Catapult's in-house O&M simulation tool. One strategy comprises of having a SOV performing most of the maintenance on the wind farm, and the other strategy uses an offshore maintenance base (OMB) instead, which would be located next to the offshore substation and would accommodate three CTVs. This paper provides an overview of the tool and the inputs used to run it, including failure rates of floating wind turbine subsea components and their replacement costs. In total six types of simulations were run with two strategies, two different weather limits for CTVs and two weather datasets ERA5 and ERA-20C. The results of this study show that the operational expenditure (OPEX) costs for the strategy with an OMB are 5%-8% (depending on the inputs) lower than with SOV, but if capital expenditure (CAPEX) costs are included in the analysis and the net present value (NPV) is taken into account then the fixed costs associated with building the offshore maintenance base have a significant impact on selecting a preferred strategy. It was found that for the case study presented in this paper the OMB would have to share the foundation with a substation in order to be cost competitive with the SOV strategy.
ORCID iDs
Avanessova, Nadezda, Gray, Anthony, Lazakis, Iraklis ORCID: https://orcid.org/0000-0002-6130-9410, Thomson, R Camilla and Rinaldi, Giovanni;-
-
Item type: Article ID code: 79630 Dates: DateEvent14 April 2022Published19 January 2022Accepted24 October 2021SubmittedSubjects: Technology > Hydraulic engineering. Ocean engineering Department: Faculty of Engineering > Naval Architecture, Ocean & Marine Engineering Depositing user: Pure Administrator Date deposited: 16 Feb 2022 09:04 Last modified: 11 Nov 2024 13:21 URI: https://strathprints.strath.ac.uk/id/eprint/79630