How far does the power need to go? The impact of GB-wide transmission network capacity on wind curtailment and access to low carbon electricity

Gill, Simon and Bell, Keith (2024) How far does the power need to go? The impact of GB-wide transmission network capacity on wind curtailment and access to low carbon electricity. ORE Catapult. (https://doi.org/10.17868/strath.00091062)

[thumbnail of Full-Report-Gill-and-Bell-2024-How-far-does-the-power-go]
Preview
Text. Filename: Full-Report-Gill-and-Bell-2024-How-far-does-the-power-go.pdf
Final Published Version
License: Creative Commons Attribution 4.0 logo

Download (6MB)| Preview
[thumbnail of Executive-summary-How-far-does-the-power-need-to-go]
Preview
Text. Filename: Executive-summary-How-far-does-the-power-need-to-go.pdf
Final Published Version

Download (1MB)| Preview

Abstract

This project explores the question of how much capacity on the national, main transmission network is economically efficient given the likely capacity, type and spatial distribution of generation and the magnitude and location of demand in a decarbonised electricity system. It has been undertaken through a partnership between the University of Strathclyde, the Offshore Renewable Energy Catapult, and The Energy Landscape. The project explores some important consequences of our transition to a decarbonised electricity system, an ambition which UK Government has targeted to achieve for 2035 [1].

ORCID iDs

Gill, Simon and Bell, Keith ORCID logoORCID: https://orcid.org/0000-0001-9612-7345;